GeorgetownWednesday, November 18
Georgetown's planning commission recommends denying a data center rezoning after a packed hearing
The Daily Round Rock team
Georgetown's Planning and Zoning Commission voted unanimously to recommend denying a rezoning for a proposed data center Tuesday night. More than 100 people signed up to speak, and residents packed council chambers, the lobby and the sidewalk over a proposed 68-megawatt project near their homes. The Statesman reported that the project has also prompted questions from nearby residents about transparency.
KXAN reported residents spoke out about noise, water use and power reliability. Developer representative Phillip Niels said the site would use low-level lighting and was designed to limit noise. He estimated $10 million to $15 million a year in property taxes.
“It's too close to houses. It will ruin any other development in that area. And we need a grocery store out there.”
- Site: about 28 acres near East University Avenue and Northeast Inner Loop
- Project: one building called Inner Loop Exchange, with on-site generators
- Request: raise the footprint cap from 5,000 to 290,000 square feet
The requested footprint is 290,000 square feet
Floor area of the proposed data center, beside places you know
5 football fields would fit inside the proposed data center
Source: KEYE
View as table
| Floor area | |
|---|---|
| The proposed data center | 290,000 sq. ft. (Requested footprint cap) |
| A football field | 57,600 sq. ft. (end zones included) |
| A Walmart Supercenter | about 180,000 sq. ft. |
The commission's vote doesn't reject the proposal. City Council is expected to take it up Dec. 8.
6-1council vote needed to overturn the denial recommendation
Georgetown City Council is expected to consider the rezoning on Dec. 8.
Source: KEYE
Sources: KEYE, KXAN Austin, KVUE, Austin American-Statesman